Browse › Chesterfield County › Data center
Chirisa Richmond LLC
on Virginia DEQ's records · 1401 Meadowville Technology Pkwy, Chester 23836 · Chesterfield County · ZIP 23836
Air permits
- 52432-6, issued Apr 9, 2026 (Article 6 - mNSR)
Timeline
What the official records show for this site, oldest first: county filings, DEQ air permits, and changes the daily check has seen on DEQ's records since Sep 28, 2026. County filings within 0.25 miles are placed here by this site, by location only: they may be a different project, so check the county record.
- Apr 9, 2026 DEQ Air permit 52432-6 issued: minor new source review (Article 6).
- Date not published County Site plan 25PR1033 filed with Chesterfield County: CTP-03 DATA CENTER - PLASE 1. Status now: Site plan approved. Matched by location (0.02 mi away)
- Date not published County Site plan 25PR1203 filed with Chesterfield County: CTP-03 DATA CENTER - PHASE 2. Status now: Site plan approved. Matched by location (0.02 mi away)
- Date not published County Site plan 24PR1076 filed with Chesterfield County: CTP-02 DATA CENTER. Status now: Site plan approved. Matched by location (0.02 mi away)
Its permits on DEQ's list are minor new source review (Article 6) permits. DEQ requires a public comment period for permits for major sources (Title V, PSD, nonattainment new source review and Acid Rain); these permit types aren't on that list.
Any open comment period on an air permit is listed on DEQ's Air Public Notices page, and DEQ's email alerts ("Public Notice-Air") announce them; this site doesn't track them. Whether a data center needs a local vote depends on the site's zoning: where it needs a rezoning or special exception, the county or city board decides, usually after a public hearing: see the county's or city's own board and planning commission pages. (DEQ's rules as its notices page describes them, checked Oct 12, 2026.)
Construction stormwater permits
1 DEQ construction stormwater permit that mentions a data center, within 0.5 miles of this site and nearer to it than to any other DEQ-listed data center (this site's match, by location). These are registrations for coverage under DEQ's general permit for stormwater from construction sites (VAR10). Start and end dates are the operator's estimates on DEQ's record.
Schools within 2 miles
- Elizabeth Scott Elementary (Chester), 1.59 mi
- Elizabeth Davis Middle (Chester), 1.90 mi
Other data centers within 1 mile
County filings within 2 miles
4 filings (land-use applications and site plans) that mention a data center, from Chesterfield County, Loudoun County, Prince William County, Spotsylvania County and Stafford County records; 0 still in county review. Filings come before any DEQ air permit, so some of these may not be on DEQ's records yet.
-
CTP-03 DATA CENTER - PLASE 10.02 mi
-
CTP-03 DATA CENTER - PHASE 20.02 mi
-
CTP-02 DATA CENTER0.02 mi
Who represents this area
State legislators: Who's My Legislator (Virginia General Assembly) shows your Virginia House of Delegates and Senate districts, for any address.
Electric utility
This data center is inside the approximate service area of:
- Dominion Energy Virginia: average residential bill $157.75 a month in 2025, 15.2¢ per kWh
From the federal electric retail service territories layer (U.S. Department of Energy), which is approximate near boundaries: your bill names your utility. Averages are this site's calculation from EIA Form 861 (2025), across all of the utility's customers, not anyone's bill. Rates are set for the utility as a whole, not by what's built nearby.
Source
DEQ Air Sites record 52432 (permit class: Synthetic Minor). The stage is DEQ's own. This page is rebuilt every morning from DEQ's records.
Follow changes here
New data centers, stage changes and air permits on DEQ's records, and county filings, at this site (county filings within 0.25 miles), as the daily check finds them: RSS feed for this page. Paste that link into any feed reader (many can also send updates by email). There's nothing to sign up for, so this site never knows who follows.
No changes at this site (county filings within 0.25 miles) since the daily check began on Sep 28, 2026.