Electricity and data centers in Virginia
What official sources say about how data center growth affects electricity costs. Checked 2026-10-16; every statement links to its source. Projections are labeled as projections, and studies paid for by a company or an advocacy group are listed separately at the end.
How electricity rates are set
Your rates aren't set by what's built near you. The State Corporation Commission (SCC) sets rates for each utility and each class of customer, so a data center affects the rates of the utility that serves it, wherever that utility's customers live. Which utility serves you depends on where you live: Dominion Energy Virginia, Appalachian Power, an electric cooperative or a town or city utility.
What the SCC decided for Dominion
In Dominion's 2025 biennial review (Case PUR-2025-00058, final order of November 25, 2025):
- A separate rate class for very large customers (GS-5), from January 1, 2027: customers with a measured or contracted demand of 25 megawatts or more on one site and a load factor of at least 75%. The SCC says this lets it set their rates separately "to recover the unique costs of providing them with electric service, minimizing cost shifting" (SCC fact sheet, February 2026).
- Minimum charges: 85% of contracted demand for distribution and for transmission, and 60% for generation, regardless of how much electricity the customer uses; a minimum contract of 14 years; and collateral requirements for new customers from 2027.
- Cost allocation: Dominion must propose other ways of allocating generation and transmission costs.
- Overall rates: the SCC approved base-rate increases of $565.7 million for 2026 and $209.9 million for 2027, which it put at $11.24 and $2.36 a month for a typical residential customer (SCC news release). These are the results of the whole rate case, not an estimate of the effect of data centers.
- The SCC says it is reviewing similar safeguards for Appalachian Power and the electric cooperatives.
What the General Assembly passed
SB 253 became law as Chapter 1124 of the 2026 Acts of Assembly (effective July 1, 2026). Among other things, it directs Dominion, in rate cases starting after January 1, 2027 and before July 1, 2033, to propose allocating certain capacity-procurement and distribution-investment costs to the class of customers with 25 megawatts or more and a load factor of 75% or more, and it extends Dominion's and Appalachian Power's energy assistance and weatherization pilot programs to 2038.
What official studies project
The General Assembly's Joint Legislative Audit and Review Commission (JLARC) studied data centers in 2024 (report page):
- "Data centers are currently paying their full cost of service, but growing energy demand is likely to increase other customers' costs."
- A projection: for a typical Dominion residential customer, generation- and transmission-related costs could rise by about $14 to $37 a month by 2040, in constant (inflation-adjusted) dollars, depending on how much data center demand is built for.
- A separate data center rate class, changed cost allocation and more frequent rate adjustments "could help insulate non-data center customers".
The technical analysis behind JLARC's study, by the consulting firm E3 for JLARC (presentation), also projects that under current rate structures data centers would bear a larger share of the added costs than residential customers, and that rate reviews every two years lag behind growth this fast.
The regional grid
Dominion's customers are part of PJM, the regional grid operator, whose capacity auctions set part of what utilities pay for power supply. PJM's 2026/2027 auction cleared at its price cap of $329.17 per megawatt-day. PJM's independent market monitor estimates that data center load raised that auction's capacity costs by about 82% (its analysis); that is the monitor's own estimate, not a PJM figure.
Where the evidence is thin
- How much of any rate increase is due to data centers is disputed; the figures above come from different methods and shouldn't be added together.
- Projections depend on how much data center demand is actually built, which is uncertain.
- The new rate class and cost allocation rules start in 2027; their effect on other customers isn't known yet.
Other studies (paid for by a company or an advocacy group)
These are listed so readers can find them; this site doesn't adopt their conclusions.
- A study by E3 commissioned by Amazon (December 2025), which found that the Amazon data centers it studied bring in more revenue than their cost to serve: E3's page.
- Testimony by the Piedmont Environmental Council in Dominion's 2025 rate case: PUR-2025-00058 testimony.
How to take part
SCC cases take public comments, and some hold public hearings: search a case on the SCC's case search. New power lines near you are listed on this site's take-part page.