25 filings (land-use applications and site plans) that mention a data center, from Loudoun County records; 10 still in county review. Filings come before any DEQ air permit, so some of these may not be on DEQ's records yet.
-
45865 MARIES RD REZONING : A Zoning Map Amendment to rezone 10 acres from A-3 to PD-IP and a Special Exception to permit a maximum 1.0 FAR for data center use.
-
45865 MARIES RD REZONING : A Zoning Map Amendment to rezone 10 acres from A-3 to PD-IP and a Special Exception to permit a maximum 1.0 FAR for data center use.
-
45865 MARIES ROAD : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR SITE IMPROVEMENTS FOR DATA CENTERS, IN THE PLANNED DEVELOPMENT INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
(Conditional Approval) CLARKE HOOK CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) TO CONSTRUCT ONE DATA CENTER, IN THE PLANNED DEVELOPMENT - INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
(Conditional Approval) RIDGETOP CENTER : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF TWO DATA CENTER BUILDINGS, IN THE PLANNED DEVELOPMENT - INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
HORSESHOE DRIVE: A Special Exception to allow for a 1.0 floor area ratio (FAR) of data center uses.
-
HORSESHOE DRIVE: A Special Exception to allow for a 1.0 floor area ratio (FAR) of data center uses.
-
(Conditional Approval) HORSESHOE DRIVE : REQUEST APPROVAL OF A SITE PLAN (STPL) TO BUILD A DATA CENTER, IN THE PLANNED DEVELOPMENT - INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
(Conditional Approval) MANEKIN PLAZA : REQUEST APPROVAL FOR A SITE PLAN (STPL) TO CONSTRUCT ONE DATA CENTER, IN THE PLANNED DEVELOPMENT - INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
THAYER RD DATA CENTER SPAM: THIS SPAM IS TO ADJUST THE BUILDING HEIGHT OF THE PROPOSED BUILDING FROM 45' TO 65'. NOTE THAT THE SIGNING ENGINEER FOR GORDON IS ONLY VALIDATING THE CHANGE IN BUILDING HEIGHT ON THE CLOUDED…
-
(Conditional Approval) Thayer Road - This project consists of a proposed 2-story data center with a road around it, utilities, and other associated infrastructure.
-
(Conditional Approval) DULLES DESIGN DATA CENTER: Proposed 2-Story Data Center (STPL)
-
45360 SEVERN WAY DATA CENTER : REQUEST APPROVAL OF A SITE PLAN AMENDMENT (SPAM) TO THE PREVIOUSLY APPROVED SPAM-2017-0038 FOR A WATER TANK EXPANSION AND PARKING RECONFIGURATION, IN THE PLANNED DEVELOPMENT - INDUSTRIAL…
-
CORSCALE VA2 BLDG 1 (SPAM): Revision to STPL-2022-0012, a data center within the Kincora IP District.
-
CORSCALE VA2 BLDG 1 : REQUEST APPROVAL OF A SITE PLAN (STPL) FOR THE CONSTRUCTION OF A DATACENTER BUILDING, IN THE PLANNED DEVELOPMENT- INDUSTRIAL PARK (PDIP) ZONING DISTRICT.
-
DULLES 28 TECHNOLOGY PARK : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE PROPOSED DEVELOPMENT OF TWO DATA CENTER BUILDINGS AND WHOLESALE/FLEX INDUSTRIAL BUILDINGS, IN THE PLANNED…
-
Site Plan for development of 3 Data Center Buildings
-
BUILDING VA15 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE CONSTRUCITON OF DATA CENTER BUILDING WITH ASSOCIATED SURFACE PARKING, DRIVE AISLE, AND UTILITY INFRASTRUCTURE, IN THE (PDOP) PLANNED…
-
BUILDINGS VA 13 AND 14 : REQUEST APPROVAL OF A SITE PLAN AMENDMENT (SPAM) FOR THE CONSTRUCTION OF 735,714 SF OF DATA CENTER/OFFICE FLOOR AREA, IN THE PLANNED DEVELOPMENT OFFICE PARK (PDOP) ZONING DISTRICT.
-
BUILDINGS VA 13 & VA 14 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR THE CONSTRUCTION OF +/- 729,298 SF OF DATA CENTER/OFFICE FLOOR AREA INCLUDING ALL RELATED INFRASTRUCTURE, UTILITIES, ETC. IN THE…
-
VANTAGE-VA22 : REQUEST APPROVAL OF A SITE PLAN (Fast Track) for the construction of Data Center, circulation drives, and associated infrastructure on landpreviously developed under. (PDIP) ZONING DISTRICT.…
-
VANTAGE VA21 : REQUEST APPROVAL OF A MODIFIED PROCESS SITE PLAN (STMP) FOR A PROPOSEDDATA CENTER BUILDING AND ALL OF THE ASSOCIATED INFRASTRUCTURE INCLUDING SWM AND BMP VAULTS, IN THE PLANNED DEVELOPMENT- INDUSTRIAL…
-
VANTAGE DATA CENTER : A Zoning Map Amendment application to bring all seven parcels within the PD-IP district governed by the most updated version of the Revised1993 Loudoun County Zoning Ordinance.
-
VANTAGE DATA CENTER : A Special Exception application to increase the FAR on the Property from a .60 to a 1.0. in order to establish a data center on the property.
-
STACK ASHBURN DATA CENTER (SPAM): This is a Site Plan Amendment to STPL-2020-0005 Stack Ashburn Data Center for the relocation of tree conservation landscaping necessitated by the proposed Loudoun Water Reclaim Water…